What worries distribution managers most about changing systems is not choosing the new one but cut-over day: will invoicing stop, will client balances be lost, will reps know what is on their vans? These fears are fair, and the answer is a clear plan that starts weeks before cut-over.
What gets migrated?
| Data type | Examples | Migrated? |
|---|---|---|
| Master data | Items, units, codes, clients, suppliers, price lists | Yes, in full after cleanup |
| Opening balances | Stock per warehouse and van, client and supplier balances | Yes, on cut-over day |
| Open documents | Uncleared post-dated checks, unpaid invoices | Yes, in detail |
| Historical transactions | Past years' invoices and movements | As far as reports and comparison need |
Clean before you move
- Duplicate items: the same item under different names. Merge them first.
- Inactive items: items that have not moved in years. Deactivate them rather than migrate them as active.
- Units of measure: review conversion factors, especially in sectors that buy in one unit and sell in another.
- E-invoice codes: make sure every active item is coded, as in the e-invoicing guide.
- Client data: tax numbers, addresses, locations and credit limits.
The cut-over plan
- 1
Operations study
Sessions with warehouse, sales and finance teams to understand current work and decide what moves.
- 2
Cleanup and preparation
Merge items and clients, review units and codes, and prepare migration files.
- 3
Trial migration
A full move to a test environment, with balances and reports matched against the old system.
- 4
Training
Each team trained on its own screens and daily scenarios using the trial data.
- 5
Cut-over day
Close the old system, run a blind count, move final balances and start work.
- 6
First-weeks follow-up
Daily follow-up in the first weeks, with issues solved the same day.
Cut-over day: what exactly happens?
Pick a quieter day, such as the start of a week or after a month-end close. The day before, transactions are closed in the old system, stock and van custody are counted blind as in the blind count guide, and client balances and open checks are matched. Final balances are then moved, and work starts on the new system in the morning.
Rushed cut-over
- No trial run beforehand
- Balances moved without matching
- Training in go-live week
- Support on demand only
Planned cut-over
- A full trial run with matching
- A blind count before moving balances
- Training on real data in advance
- Daily follow-up in the first weeks
Parallel running: do you need it?
Some suggest running both systems for a while. In distribution this usually doubles the work and creates conflicting numbers, because every transaction is entered twice. A good trial migration before cut-over and close follow-up after it are the better choice.
To reduce risk further, start with the core apps and add others later, as explained in modular ERP.
Plan your move with the TASTO teamOperations study, migration of items, clients and balances, training and go-live follow-up.